Project Management

Showing 76-150 of 258 answers

Estimating the number of periods that is needed to complete individual activities
  • Activity duration estimating
  • Activity definition
  • Activity sequencing Correct
  • Activity resource estimating
Every Organization maintains a repository of information and data from the past Projects what do you call this
  • Organizational Records
  • Organizational process assets Correct
  • Financial and market conditions
  • Regulatory environment
Framework that Leaders believe in people and communicate that belief; they are visible and accessible; they empower, increase participation, support, share information, and move decision making down into the organization
  • Political Framework
  • Human Resources Framework Correct
  • Structure framework
  • Symbolic Framework
Gannt Chart is a visual representation that breaks down the scope of the project into manageable sections for the team
  • True
  • False Correct
Graphs pairs of numerical data, one variable on each axis, to look for a relationship The closer data points are to a diagonal line, the more closely the two variables are related
  • Scatter Diagram Correct
  • Histogram
  • Pareto Chart
  • Control Chart
Here all allowable expenses are charged back and in addition an incentive fee for exceeding the performance criteria specified in the contract
  • None of the given
  • Cost plus fixed fee
  • Cost plus incentive fee Correct
  • Cost plus fee
Here all allowable expenses are charged back plus a fixed fee at the end of the contract The fixed fee is how the seller makes their profit
  • Cost plus fixed fee Correct
  • None of the given
  • Cost plus incentive fee
  • Cost plus fee
Here the seller is reimbursed for allowable costs plus a fee that's calculated as a percentage of costs
  • Cost plus incentive fee
  • Cost plus fee Correct
  • none of the given
  • Cost plus fixed fee
How often does the Planning Process Group occur
  • Only once in the project or phase
  • As many times as is necessary to achieve the project objectives Correct
  • Not at all in a small project
  • It only happens at program level
Identifies many possible causes for an effect or problem and sorts ideas into useful categories
  • Histogram
  • Cause-and-effect diagram Correct
  • Control Charts
  • Check sheet
Identifying, analyzing, and responding to risks related to the project
  • Project threat management
  • Project peril management
  • Project liability management
  • Project risk management Correct
If the vice president of sales initiates a project to improve direct product sales using the Internet, he or she might be the _____
  • Project Management Professional (PMP)
  • project sponsor Correct
  • project manager
  • program manager
In RACI it's the person who signs off on the task or has authority for it?
  • Consultation
  • Informed
  • Accountability Correct
  • Responsibility
In RACI Who does the task?
  • Responsibility Correct
  • Informed
  • Accountability
  • Consultation
In which document will you find details of the procedures and processes to follow when you are closing contracts?
  • Procurement Management Plan
  • Project Management Plan
  • Change Management Plan
  • Contract Terms and Conditions Correct
Includes the processes required to manage timely completion of the project
  • Schedule
  • Milestone
  • Project time schedule
  • Project time management Correct
Influencing is also referred to as _____________
  • All of the given Correct
  • Motivating
  • Directing
  • Staffing
Invest 2,000 now, receive 3 yearly payments of 100 each, plus 2,500 in the 3rd year Use 10% Interest Rate
  • 256
  • 130
  • 12697 Correct
  • 335
Is a document that request support-usually money- for work a proposer wants to do?
  • External Document
  • Proposal Correct
  • Business Plan
  • Internal Document
Is a method for determining the estimated annual costs and benefits for a project
  • Currency flow
  • Cash flow Correct
  • Money flow
  • Cash movement
Is a set of activities, to plan, monitor, coordinate and review goals
  • Management
  • Project Planning
  • Scope Planning
  • Project Management Process Correct
Is a team structure with members from functional areas, depending on skills required
  • Matrix Organization Correct
  • Project Control
  • Project Planning
  • Project Scheduling
Is a type of proposal address someone within your organization
  • Business Plan
  • External Proposal
  • Internal Proposal Correct
  • Proposal
Is a type of proposal address to an independent organization or individual from another such entity
  • Proposal
  • Internal Proposal
  • External Proposal Correct
  • Business Plan
Is a very important part of the proposal because it provides a short overview and summary of the entire proposal
  • Abstract Correct
  • Table of Content
  • Introduction
  • Title Page
Is made up of individuals from various areas and department within a company
  • Project Manager
  • Top Management
  • Stakeholders
  • Project team Correct
Is the degree to which a set of inherent characteristics fulfills requirements
  • Fitness for use
  • Reliability
  • Quality Correct
  • Conformance to requirements
Is the term used to describe formal systems devised for the management of people within an organization requirements
  • Human Resource Management Correct
  • People Management
  • Systems Application
  • Human Application Systems
Is very important in planning procurements Many potential suppliers are often available for goods and services, so the project team must choose suppliers carefully
  • financing analysis
  • make-or-buy analysis
  • market research Correct
  • none of the given
It addresses the business, technological, and organizational issues associated with creating, maintaining, and modifying a system
  • System design
  • System implementation
  • System management Correct
  • Systems analysis
It describes your company philosophy in a few sentences, describes how you see your company in the future
  • Goals
  • Company Information
  • General Business Overview
  • Mission and Vision Statement Correct
It identifies and document the relationship between project activities
  • Activity sequencing Correct
  • Activity resource estimating
  • Activity duration estimating
  • Activity definition
It is a contract all the costs that the seller incurs during the project are charged back to the buyer
  • Fixed Price
  • Stable price
  • Time and Material
  • Cost reimbursable Correct
It is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time
  • Payback Analysis
  • Balance Scorecard
  • ROI Correct
  • NPV
It is a set of activities to plan, monitor, coordinate and review a goal
  • Project
  • Blueprint
  • Plan
  • Project management Correct
It is similar to a deliverable-oriented WBS except that it is organized, at the highest level, by phases or steps in a process rather than by deliverables
  • Procedure WBS
  • Process Centered WBS Correct
  • Procedure Centered WBS
  • Centered WBS
It maps the work of the project, as described in the WBS, to the people responsible for performing the work, as described in the OBS
  • WBS
  • OBS
  • RACI
  • RAM Correct
It refers to mutually binding agreement between seller and the buyer
  • Deal
  • Pact
  • Contract Correct
  • Treaty
It refers to the achievement of a key deliverable
  • dependencies
  • milestones Correct
  • implementation plan
  • resource plan
It refers to the beginning or ending point of one or more activity
  • Event Correct
  • Network
  • Activity
  • Operation
It refers to the method by which items are purchased from external suppliers
  • Outsourcing
  • Contracting
  • Payment
  • Procurement Correct
It's a process that can be applied in a collaboration of its various sub-disciplines
  • Project Control
  • Project Collaboration Correct
  • Project Motion
  • Project Activity
It's a schematic display of the logical relationship among, or sequencing of project activities
  • critical path
  • Work breakdown structure
  • resource histogram
  • network diagram Correct
It's the 2nd Habit of a highly effective person
  • Think Win-Win
  • Begin with the end in mind Correct
  • Put Things First
  • Be Proactive
Its about keeping the project on track
  • Accomplishing
  • Motivating
  • Controlling
  • Leading Correct
Kick-off" meeting usually marks the start of the Project Execution phase where the teams involved are informed of their responsibilities
  • True Correct
  • False
known for his work on quality control in Japan, and he developed the 14 Points for Management in his text Out of the Crisis
  • Isakawa
  • Deming Correct
  • Juran
  • Crosby
Leadership behavior that focus on arrangement, strategy, environment, implementation, experimentation, and adaptation
  • Political Framework
  • Human Resources Framework
  • Structure framework Correct
  • Symbolic Framework
Leadership style that demands immediate compliance
  • Pacesetting
  • Commanding Correct
  • Visionary
  • Democratic
Leadership style that sets high standard for performance
  • Visionary
  • Pacesetting Correct
  • Commanding
  • Democratic
Main output of _________ is schedule management plan
  • planning schedule board
  • planning schedule management Correct
  • planning Gannt Chart
  • scheduling list management
Most proposals discuss the advantages or benefits of doing the proposed project This acts as an argument in favor of approving the project
  • Background
  • Benefit and feasibility Correct
  • Schedule
  • Description of work
Motivation causes people to do something for a reward or to avoid a penalty
  • Social Motivation
  • Intrinsic motivation
  • Extrinsic motivation Correct
  • Self motivation
Network diagrams are the preferred technique for showing activity sequencing
  • True Correct
  • False
One of the leadership style that shows self confidence, empathy and change catalyst
  • Visionary Correct
  • Democratic
  • Commanding
  • Pacesetting
One of the role of PM is to includes developing and managing the direction of the project
  • Quality Management
  • Integration Management Correct
  • Scope management
  • Time and cost management
Outline the corporate structure, Are you a sole proprietor, partnership or an incorporation? List any shareholders, partners and incorporation information
  • Company Structure Correct
  • Location
  • General Business Overview
  • Key Personel
Part of the proposals contain a section that shows not only the projected completion date but also key milestones for the project
  • Background
  • Schedule Correct
  • Introduction
  • Benefits and feasibility study
Pessimistic time he shortest possible time in which an activity is likely to be completed
  • True
  • False Correct
Project ________ management ensures that the project will satisfy the stated or implied needs for which it was undertaken
  • quality Correct
  • cost
  • scope
  • time
Project ________ management involves acquiring goods and services for a project from outside the performing organization
  • human resource
  • risk
  • procurement Correct
  • communications
Project ________ management involves defining and managing all the work required to complete the project successfully
  • cost
  • quality
  • time
  • scope Correct
Project charter inputs includes project management plan, approve change request, organizational process assets
  • True
  • False Correct
Project is a temporary endeavor undertaken to create a unique product, service, or result
  • True Correct
  • False
Project Management Institute (PMI)suggested 7 phases of project management
  • True
  • False Correct
Project Management involves four project constraints they are time, cost, human resources and scope
  • True
  • False Correct
Project Management is the discipline of ________ sources to achieve a specific goal
  • Securing and managing
  • All of the given Correct
  • Organizing
  • Planning
Project Management plan is a document used to coordinate all project planning documents and help guide a project's execution and control
  • True Correct
  • False
Project management software helps you develop a ______, which serves as a basis for creating Gantt charts, assigning resources, and allocating costs
  • deliverables
  • Project plan
  • WBS Correct
  • schedule
Project manager ensures that _____________
  • Both of the given Correct
  • The project will get delivered on time
  • None of the given
  • The project will get completed within budget
Project Planning is a discipline for stating how to complete a project within a certain timeframe
  • True Correct
  • False
Project Scope Management is the management of the process that is required to ensure that a project includes all the work necessary to complete the project successfully
  • True Correct
  • False
Project Team is the composition of individuals from various areas and departments within a company
  • True Correct
  • False
Project work involves overseeing activities to meet the performance objectives of the project
  • Direct and Manage Project Work Correct
  • Monitor and Control Project Work
  • Develop Project Charter
  • Develop Project Management Plan
Proposal to an independent organization or individual from another such entity is one written from one separate, independent organization or individual to another such entity
  • Internal
  • Unsolicited
  • External Correct
  • Solicited